top of page
H2Flow Tanks Logo

Epoxy Coated

Industrial

Industrial Process Tanks

Greenland
COATING

Epoxy Coated

ROOF TYPE

Tapered Beam

# of Tanks

3

TOTAL VOLUME

645

Project Description

Amaroq Minerals is developing a gold mine in Greenland, and selected H2Flow Tanks & Systems to supply the water storage infrastructure for their process plant. H2Flow delivered three epoxy-fused-to-steel bolted tanks, each fitted with heaters and mixers to ensure reliable performance in demanding arctic conditions.

H2Flow Tanks supplied three bolted epoxy-fused-to-steel tanks complete with integrated heaters and mixers. The tanks serve distinct roles within the process plant: process water supply, clean and fire water reserve, and surge capacity for the tailings management facility (TMF). The use of epoxy-fused-to-steel construction provides durable, corrosion-resistant storage suited to the remote and challenging operating environment.

Project Details

Location

Greenland

Sector

Industrial

Contractor/Engineer

Haylard

Installation Date

October 2025

Tank Information

  • Process Water Tank - 210 m³

  • Clean / Fire Water Tank - 425 m³

  • TMF Surge Tank - 210 m³

Project Photos

bottom of page